240D LC Excavator Production Estimating Program
|
|
ESTIMATING PURPOSES
ONLY |
|
Program
calculates hourly production to load dump trucks, trenching, charge hoppers,
etc.
|
|
Production
is continuous except for excavator repositioning (no wait time for dump
trucks).
|
|
Place
cursor on red triangles for explanation.
Swing cycle times are based on proper
|
|
|
matching of
arm, bucket, and material.
|
|
|
|
Use Tab Key
|
|
|
Material
Density (lbs. per loose cubic
yard)
|
|
|
|
|
Or Material Density (lbs. per bank cubic yard)
|
|
|
|
|
If bank cubic yards, enter load factor (See
above)
|
|
|
|
|
Excavator
Bucket Size (heaped c.y.)
|
|
|
|
|
Bucket Fill Factor (See
above)
|
|
|
|
|
Average
Horizontal Distance from Load Point to Discharge (ft.)
|
|
|
|
|
Average
Vertical Distance from Load Point to Discharge (ft.)
|
|
|
|
|
If excavating from a trench, what is the average depth?
|
|
|
|
|
|
feet of total vertical lift, how
many are in the trench?]
|
|
|
|
|
Material
Composition for Bucket Loading Speed
(Enter an x in the
appropriate yellow cell)
|
|
|
Loose
|
|
Medium
|
|
Hard
|
Other
|
|
|
|
|
|
|
|
|
|
|
|
Sec's:
|
2
|
2.5
|
3
|
4
|
5
|
|
|
|
|
|
If Other Selected, Enter
Sec.
|
|
|
|
|
|
|
Dumping
Speed (Enter an x in the
appropriate yellow cell)
|
|
|
|
Fast
|
|
Medium
|
|
Slow
|
Other
|
|
|
|
|
|
|
|
|
|
|
|
Sec's:
|
1.5
|
2
|
2.5
|
3
|
5
|
|
|
|
If Other Selected, Enter
Sec's:
|
|
|
|
|
|
|
|
|
|
(Enter an x
in the appropriate yellow cell below right)
|
|
|
|
Repositioning
and Dressing/Cleaning Allowance (5 Sec's. Allowance Each)
|
|
|
Excavator
Remains Stationary for Long Periods, No Dressing
|
|
|
|
Repositions
Every 5 Cycles; Minimal Dressing
|
|
|
|
|
Repositions
and Dresses Every 5 Cycles
|
|
|
|
|
Repositions
Every 3 Cycles; Dresses Every 5 Cycles
|
|
|
|
|
Other
|
|
|
|
|
|
If
OtherSelected, Enter Number of Cycles Before Repositioning and
Dressing
|
|
|
Repositioning
|
|
Dressing/Cleaning
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Average Excavator Cycle Time
|
|
|
|
Load
|
|
|
|
|
|
Dump
|
|
|
|
|
|
Swing
|
|
|
|
|
Allowance
|
|
|
|
|
Total
|
|
Sec's.
|
|
Hourly
Production
|
|
|
|
50 Min
|
60 Min.
|
|
|
Rounded Estimate
|
|
Sec's.
|
Loose Cubic Yards
|
|
|
|
|
|
|
Bank Cubic Yards
|
|
|
|
|
|
|
Tons
|
|
|
|
|